Heavy Lifting News

Case Studies on Innovative Problem Solving

Incremental Bridge Launching Used To Construct Kentucky’s Tallest Bridge

05/15/2022

A unique approach to bridge construction was recently used to construct the Pond Creek Bridge on US460 in Pike County, Kentucky. Incremental bridge launching, which is popular in Europe but relatively uncommon in the US, is ideal when a bridge is very high and access via traditional cranes is difficult or impractical.

Bush and Burchett Inc. of Allen, Kentucky, was contracted to construct what would become the tallest bridge in the Bluegrass State and one of the tallest traffic bridges in the country. The rugged terrain (see photo above) of the project site and the bridge’s height of 324 feet created unique challenges for the construction project.

According to Paul Burchett, co-founder of Bush & Burchett, “Being 320’ tall and only 1000’ long, the slopes on each side of the bridge were extremely steep. This made conventional erection almost impossible.”

Bush and Burchett determined the safest and most economical strategy was to build the steel bridge on the embankment and incrementally move the girders into position on the eight sets of piers. The contractors partnered with Engineered Rigging for this segment of the bridge construction.

The equipment utilized included two 70-ton strand jack rentals (models HSL7006), a SLPP7E strand jack pump, strand guide, strand recoiler, gold box, a laptop and industrial Hilman rollers. In addition to fulfilling the construction equipment rental, Engineered Rigging provided an on-site technician to operate the strand jack system. As construction of one section of girders was completed in the launch bay, the strand jack system was used to pull it onto the bridge pier, thus allowing the next section of the bridge to be constructed on the embankment.

Overhead view of Pond Creek Bridge project.
Workers launching a beam on the Pond Creek Bridge.

In total, 10 jacking evolutions are necessary to pull the entire bridge into position of which 8 are currently complete. The pulling weight for the first pull was approximately 16,000 lbs, and the bridge became heavier with each subsequent pull, the heaviest reaching 80,000 lbs. Pulling force is a function of how easily the bridge slides on the Hilman rollers and the dead weight of the steel span.

According to Burchett, “The launch went as well as we could have imagined. We encountered a few challenges during the launch related to the small margin for tolerances. On the piers, we only had about a half inch tolerance with each gap. Any lateral movement of the girders or minimal inconsistencies in fabrication of the girders or rollers led to rollers not lining up with the gap in the splice plates. While this caused a bit of a delay on the eastbound launch, we modified the splice plates on the westbound bridge that helped reduce the frequency of these issues.“

View of beam launch over Pond Creek Bridge from afar.

Once the launching of the bridge was complete, the bridge was lifted off the Hilman rollers to allow the bridge to sit on its bearings. This step of the bridge construction process used additional Engineered Rigging heavy lifting equipment rentals including one SFP421SJ split flow pump, hydraulic hoses, four LPL1602 locking pancake jacks (160-ton lifting capacity each), and four HCL1006 100- ton locknut cylinders.

Burchett reflected on the incremental bridge launch, “This was the first time a girder launch has ever been performed in Kentucky and I was glad to be a part of it. We would definitely use the approach again if the conditions called for it. The designer, Stantec led by David Depp, Engineered Rigging, and the inspectors with KYTC did a great job of working with us to make this happen.” 

News coverage of the project can be viewed at Progress to US 460’s Pond Creek Bridge Span Continues – YouTube.

In addition to the Pike Creek Bridge construction, Engineered Rigging has been involved in several recent bridge projects, providing innovative engineering services, design-build and fabrication solutions and heavy lifting equipment rental. You can view the case studies for the Cline Avenue Bridge in East Chicago, the Panther Island Bridges in Texas, and the demolition of the Wittpenn Bridge in New Jersey.

View of Pond Creek Bridge from below.

“Engineered Rigging was great to work with. Whatever we needed, they made happen when we needed it to happen. Our schedule would vary depending on our work and the weather, and ER made late adjustments to their schedule to make sure it matched ours. They are also extremely knowledgeable about their equipment and inventive when it comes to solutions for lifts or pulls. We would definitely use them again in the future.”

– Paul Burchett, Bush & Burchett

Receive our free newsletter in your inbox.

Popular Topics

During construction of a pharmaceutical plant in North Carolina, eight jack-up systems are shown holding a 245,000 pound pipe rack in position at 22 feet elevation.

Massive Pipe Rack, Multiple Challenges

Top 5 Rigging Stories of the Year

A photograph of the 50-year-old Glebe Road overpass bridge in Bermuda.

3-Inch Clearance: The Custom Lift That Saved a 50-Year-Old Bridge

Blue Origin launch site as seen from above.

Assembling Blue Origin’s New Glenn Rocket

Foxtrot SOLO 20 Motorized Dolly